20 October 2025 → 20 February 2026

Stage 1 Civil works - Wood St - Harfleur St

September 2025 → February 2026

Stage 2 Water Main works - Wood St to Ochtertyre St section

Estimated timing for Wood Street to Ochtertyre Street section - August to December 2025 

Stages of work:

Excavation and boring for Stage 2 of water main between

Wood & Ochertyre Streets

Water pipes and new hydrants installed.

Water connection made to new main.Testing & commissioning.

Water shutdowns occur at times to be notified.

Backfill areas of disturbed ground. Old main decommissioned.

Civil works commence on Stage 2 stormwater drainage.

New kerb and guttering installed. Landscaping underway.

Temporary pavement applied to road surface.

01 July 2026 → 28 February 2027

Stage 2 Civil works - Wood St to Ochtertyre St

February 2027

Stage 3 Hardinge Street Reconstruction

Estimated timing to be confirmed - Commencing February 2027

Ochtertyre St to Harfleur St  - works stages include:

Pavement resurfacing. 

Concrete medians installed.

Road line marking. 

Parking space marking. 

Signage installed.

Landscaping complete. 

Project complete.