Key Dates
Stage 2 Water Main works - Wood St to Ochtertyre St section
Estimated timing for Wood Street to Ochtertyre Street section - August to December 2025
Stages of work:
Excavation and boring for Stage 2 of water main between
Wood & Ochertyre Streets
Water pipes and new hydrants installed.
Water connection made to new main.Testing & commissioning.
Water shutdowns occur at times to be notified.
Backfill areas of disturbed ground. Old main decommissioned.
Civil works commence on Stage 2 stormwater drainage.
New kerb and guttering installed. Landscaping underway.
Temporary pavement applied to road surface.
Stage 3 Hardinge Street Reconstruction
Estimated timing to be confirmed - Commencing February 2027
Ochtertyre St to Harfleur St - works stages include:
Pavement resurfacing.
Concrete medians installed.
Road line marking.
Parking space marking.
Signage installed.
Landscaping complete.
Project complete.