Key Dates
February → June 2026
Stage 2 Water Main works - Wood St to Ochtertyre St section
Estimated timing for Wood Street to Ochtertyre Street section - late Feb to 5 June 2026
Stages of work:
Excavation and boring for Stage 2 of water main between Wood & Ochertyre Streets
Water pipes and new hydrants installed.
Water connection made to new main.Testing & commissioning.
Water shutdowns occur at times to be notified.