March → August 2026

Stage 1 Civil works - Wood St - Harfleur St

February → June 2026

Stage 2 Water Main works - Wood St to Ochtertyre St section

Estimated timing for Wood Street to Ochtertyre Street section - late Feb to 5 June 2026

Stages of work:

Excavation and boring for Stage 2 of water main between Wood & Ochertyre Streets

Water pipes and new hydrants installed.

Water connection made to new main.Testing & commissioning.

Water shutdowns occur at times to be notified.

Backfill areas of disturbed ground. Old main decommissioned.

June → July 2026

Stage 1 Pavement Works - Estimated dates

01 July 2026 → 28 February 2027

Stage 2 Civil Works - Wood St to Ochtertyre St

October 2026 → February 2027

Stage 2 Pavement Works - estimated dates