Current Works and Timing

    What is the revised timeline?

    Date 

    Activity

    18 September

    Stage 1 civil works works complete.

    18 Sept to 12 Oct

    Maintenance period. No major roadworks. ERC crews periodically onsite to undertake road maintenance activities.

    (est) 12 October – end November

    Transport for NSW returns to complete the pavement reconstruction works. Night works and asphalting resume.

    Late Nov – mid Dec 

    Linemarking, install new signage

    Mid December 

    Stage 1 of the project planned for completion

    Why has the roadwork been paused?

    • Work on the project has been impacted for various reasons which has caused a delay in the delivery program.
    • A nationwide restriction on work around telecommunication infrastructure temporarily paused essential utility relocation work. Multiple days of heavy rain early in the program also impacted work.
    • The program has been revised and work will pause in mid-September to allow time to prepare the site for large traffic volumes expected for the Deniliquin Ute Muster in the first week of October.
    • The road resurfacing program is planned to resume in mid-October after the event.

    What is happening now (until the pause)?

    • Work will continue along the road shoulders and building median strips, installing kerb and gutters, some new footpaths and doing streetscape work.
    • Edward River Council is planning to finish its civil work by 18 September, weather permitting.

    How do I get to the shops?

    • Access to Coles and Deni Plaza shops will continue from Wood Street only.
    • Access to other businesses will be maintained via Hardinge Street, for the interim period (mid-September to mid-October).
    • Driveways to businesses along Hardinge Street may need to close for a short time when road resurfacing work resumes. Alternative access from Harfleur Street can be used.

    Is my home access affected?

    • Homes along Hardinge Street will be accessible via Hardinge Street during the interim period (mid-September to mid-October).
    • Driveways to homes (and adjacent streets such as Holden Court) may need to close for a short time when road resurfacing work resumes from mid October. Residents will be advised.

    Will the road deteriorate during the pause in work?

    • During this period, Council and the project team will continue maintaining the road to ensure it remains safe and accessible.
    • Crews have prepared the road to allow for increased traffic volumes during the Ute Muster period.
    • There will be ongoing inspections and maintenance works carried out to manage any damage to the road surface.
    • The 40km/h speed restriction will remain in place to help minimise damage to the road surface.

    Why is it still a 40km/h zone?

    • The area is still a work site that needs to be kept safe for everyone using or working on the road.
    • Crews still need to access the site to do inspections and manage any damage to the road surface.
    • The 40km/h speed restriction will help minimise damage to the road surface.

    Can I park along Hardinge Street in the roadworks area?

    • You will not be able to park in areas that will be designated “no parking” after construction.
    • These areas will be signed and marked with bollards or other barriers during the interim period.

    Will the Hardinge Street/Henry Street intersection remain open during the Ute Muster period?

    Yes, the Hardinge Street/Henry Street intersection will remain open.

    Where can long vehicles park?

    • Long vehicle parking is available along Hardinge Street between the Ochtertyre Street roundabout and Wood Street. Further long vehicle parking may be found along Wood Street or adjacent streets.
    • A map of car parking places is available at Visit Deni Parking Map

    Will the potholes in the road be fixed?

    • Potholes will be fixed and the road surface prepared so it is smooth for traffic use over the interim period.
    • Any new potholes identified during the pause in work will be attended to by our work crews.

    Why is the roadwork being paused for so long?

    • The restriction on work around telecommunication infrastructure disrupted the work schedule, and meant work on the road reconstruction/asphalting could not be completed in time for the Ute Muster traffic.
    • Crews needed time to prepare the site for these large traffic volumes in the first week of October, and will be back on site at the earliest possible time following that period.

    What are the construction hours?

    Normal construction hours are Monday to Friday, 7 am to 6 pm, and Saturday, 8 am to 1 pm.

    Will work happen outside these hours?

    Some work, such as pavement sealing, will need to happen at night. Nearby residents and affected businesses have been notified and will receive reminders before night works occur.

    What happens if there is bad weather or other delays?

    Wet weather and unforeseen issues can affect the timing of construction. Council will provide updated information if key dates change.

General

    What is happening on Hardinge Street?

    Edward River Council and Transport for NSW are upgrading Hardinge Street, between Ochtertyre and Harfleur Streets, to improve safety, access, drainage and road condition for all road users.

    The works include:

    • a renewed road surface and pavement
    • concrete median strips and turning lanes
    • upgraded stormwater drainage
    • new and relocated water mains
    • new kerbs and gutters, with some new footpaths
    • new marked parking bays in safe locations
    • pedestrian refuge islands and tactile treatments
    • landscaping and greenery
    • new signage and line marking.

    What section of Hardinge Street is affected?

    The project covers a 936 metre section of Hardinge Street, which is part of the Cobb Highway, between Ochtertyre Street and Harfleur Street.

    Why is the upgrade needed?

    Hardinge Street is a busy local and regional road used by trucks, freight vehicles, buses, cars, motorcycles, cyclists and pedestrians. It also provides access to shops, businesses, homes and community facilities. The upgrade is designed to improve road safety, traffic flow, drainage, pedestrian access and the overall condition of the road.

    Who is delivering the project?

    The project is being delivered by Edward River Council in partnership with Transport for NSW.

Pavement Work

    What can I expect from night work?

    Crews will be working night shift at various times to get the paving done with minimal disruption.You might see lights at night and hear some noise from machinery and equipment if you live nearby. Call this number (24-hours) should you need assistance: 0437 969 287

    Will Holden Court be closed during pavement work?

    No, we’ll maintain access to Holden Court under traffic control while work is carried out in front of this street. Residents can ask the controller on site for access.

    Can I still get to the shops while the paving is underway?

    Yes, but you might want to avoid the roadwork and travel via Napier Street to access the entry to Harvey Norman and Mitre 10 on Harfleur Street, and the Deni Plaza/Coles entry on Wood Street.

Traffic Conditions During Construction

    Is Hardinge Street still open to traffic?

    Yes. Hardinge Street remains open, with changed traffic conditions in place. At times, some intersections or lanes may be temporarily closed or traffic may be stopped or slowed while works are underway.

    Please follow signage and the directions of traffic controllers, and drive carefully near workers and machinery.

    Are there any detours in place?

    There are no major detours in place, but there are local access changes and re-directions to help people reach shops, businesses and properties safely.

    Why is there a 40 km/h speed limit?

    The speed limit has been reduced to 40 km/h through the work zone to allow construction to continue safely along the road and to protect road users, pedestrians and workers.

    Will there be delays through the work zone?

    Yes. Some minor delays are expected during construction. Temporary traffic control will be in place when needed.

    What traffic controls are in place?

    Traffic controllers will use stop/slow signs when workers need to temporarily stop, slow or redirect traffic. Drivers must follow traffic control instructions and all posted signage.

    Will emergency services still be able to access the area?

    Yes. Emergency services access will be maintained throughout the works.

    What if my road or driveway is blocked, or the sign says “road closed” and I need to access my home?

    Talk to the friendly traffic controllers on site. They will facilitate access for you.

Coles, Deniliquin Plaza and Shopping Area Access

    How do I access Coles and Deniliquin Plaza during the roadworks?

    Vehicles and pedestrians should use the temporary access via Wood Street. This access is through the vacant block into the Deniliquin Plaza car park.

    This access should be used for Coles, Liquorland, Bakers Delight, The Reject Shop, Smokemart and Red Rose Diner.

    How do I access Harvey Norman and Mitre 10?

    Harvey Norman and Mitre 10 can be accessed from the existing (now widened) driveway on Harfleur Street.

    Can vehicles still enter the shopping centre car parks from Hardinge Street?

    No. During the current construction, entry and exit points to shopping centre car parks along Hardinge Street are closed. Shoppers should use the alternative entrances as signed.

    Can pedestrians still access Deniliquin Plaza safely?

    Yes. The temporary Wood Street entry includes a designated walking path for pedestrians, separated from the roadway by safety barriers. Pedestrians should take care and familiarise themselves with the changed traffic flow in the car park. Always watch for vehicles and stay safe.

    Is the temporary access suitable for people with disability, prams and mobility aids?

    Yes. The pathway is sealed and accessible for people using mobility aids, prams and similar equipment.

    How long will the temporary Wood Street entrance be used?

    The temporary Wood Street access will remain in place until the Hardinge Street car park entrances are reopened.

    What is the preferred traffic flow through the temporary Wood Street entry?

    For convenience and safety, vehicles entering via Wood Street should go straight ahead or turn left and continue clockwise around the shopping centre car park.

    Has parking at Coles or Deniliquin Plaza been affected?

    Only a small number of spaces have been removed to accommodate the temporary Wood Street entry. All other existing car spaces remain available unless otherwise signed.

    Which shops can I access from the temporary Wood Street entrance?

    The temporary Wood Street entrance provides access to the Deniliquin Plaza car park for Coles, Liquorland, Bakers Delight, The Reject Shop, Smokemart and Red Rose Diner.

    Which entrance should I use for Harvey Norman, Mitre 10 and Red Rose Diner?

    People visiting Harvey Norman, Mitre 10 and Red Rose Diner can use the existing driveway off Harfleur Street to access parking at Harvey Norman and Mitre 10. When leaving the carparks, use the same driveway onto Harfleur Street.

    Are all entrances off Hardinge Street to the shops closed?

    Yes. While the current roadworks are underway, entry and exit points to shopping centre car parks along Hardinge Street are closed. Please use the Wood Street or Harfleur Street access points as signed.

    Can both cars and pedestrians use the temporary Wood Street access?

    Yes. Cars and pedestrians can enter and leave the Deniliquin Plaza car park via Wood Street through the vacant block. Pedestrians should use the marked and separated walking path.

    What route should I follow inside the Deniliquin Plaza car park?

    For convenience and safety, follow the preferred clockwise traffic movement shown on the project signage and fact sheet. Please take care around construction traffic and follow signs.

    Where can I see access maps?

    Access maps are below.



    Can I still access the Return and Earn recycling point?

    Yes. Please travel around the car park in a clockwise direction to reach the Return and Earn recycling point. Do not turn right at the temporary entry.

    Can delivery vehicles still access Coles and Deniliquin Plaza?

    Yes. Light freight vehicles can access Deniliquin Plaza businesses via the temporary Wood Street entrance. Coles delivery trucks will access the Coles loading bay via the Harfleur Street entrance at Harvey Norman.

    Will access to the shopping centre change again when the project is finished?

    Yes. After the roadworks are complete, there will be some changes to the way vehicles enter and leave the shopping centre car parks. This is due to raised medians on the road and maintaining the traffic flow.

Bus Stop Changes

    Where is the bus stop next to Coles now located?

    The Hardinge Street bus stop and bus shelter next to Coles has been permanently relocated around the corner into Wood Street.

    Is the bus stop move temporary or permanent?

    The move to Wood Street is permanent.

    Is the Hardinge Street bus stop relocation already complete?

    Yes. The Hardinge Street bus stop has been relocated to Wood Street.

    What will change after the roadworks are complete?

    After the roadworks are complete, there will be some changes to how vehicles enter and leave all car parks. Council will provide more information before those permanent arrangements begin.

    What is happening to the bus stop opposite Deniliquin Plaza?

    The bus stop opposite Deniliquin Plaza near Hussey Lane will remain operational, but may shift along the street as works progress. Signage will be in place if the stop location changes.

    How will passengers know if a bus stop location changes?

    Signage will be in place to direct passengers. Passengers should follow signage and any directions from workers on site.

    Will bus services or timetables be affected?

    No. Timetables remain the same. The local bus service operator, Dysons, is involved in the changes and will communicate with passengers as needed.

Business Access and Deliveries

    Are businesses still open during construction?

    Yes. Businesses remain open and can operate as normal during construction, although access arrangements may change at times.

    How will customers access businesses during construction?

    Access arrangements vary by location. Shoppers should use the Wood Street temporary entrance for Coles and Deniliquin Plaza businesses including  Liquorland, Bakers Delight, The Reject Shop, Smokemart and Red Rose Diner.

    Shoppers should use the Harfleur Street driveway for Harvey Norman and Mitre 10. 

    Other business access arrangements will be managed with affected businesses and signposted where needed.

    How will freight and deliveries be managed?

    Light freight vehicles can access Deniliquin Plaza businesses through the temporary Wood Street entrance. Coles delivery trucks will use the Harfleur Street entrance at Harvey Norman. Other freight and delivery arrangements will be managed with affected businesses.

    What should business owners do if construction is affecting customer or supplier access?

    Business owners can contact the Project Manager, Dilip Boppidi, on 0424 904 585, or approach the construction supervisor on site. 

Property and Pedestrian Access

    Will access to my home or business be maintained?

    Yes. Access to homes and businesses will be maintained during the works wherever possible. Access may be temporarily affected at certain times, such as during intersection closures, utility relocations or night paving works. Any interruptions will be kept as short as possible.

    What happens if work is happening directly outside my property?

    Some driveways may be temporarily affected during construction, particularly when kerb, gutter, footpath or driveway works are underway. Workers on site will help manage access and affected residents or businesses will be advised where possible.

    Will my driveway be improved?

    Some residential and industrial driveways will be improved as part of the works. Where a driveway is disturbed by the project, it will be reinstated or improved as required.

    Will pedestrian access be maintained during construction?

    Pedestrian access may be affected at times. The footpaths on the Rams Oval side will be closed during water main works, with detours and signage in place. A designated pedestrian pathway is available at the temporary Wood Street entry to Deniliquin Plaza.

    Where should pedestrians walk when access arrangements change?

    Pedestrians should follow detour signage, on-site signage and directions from traffic controllers. For Coles and Deniliquin Plaza businesses, pedestrians should use the temporary access via Wood Street.

    What should people with mobility needs do if access is difficult?

    Please contact the project team or Council Customer Service to discuss specific access needs.

Parking

    Is parking affected by the roadworks?

    Yes. Some on-street parking on Hardinge Street will not be available during construction because safe work areas are needed around the construction site. Parking on private property and in business car parks will generally remain available, subject to local access changes.

    Are there temporary parking restrictions near the work zone?

    Yes. Some on-street parking will not be available during construction. Locations and timing may change as works progress. Please follow signage and directions from traffic controllers.

    How will parking change when the project is finished?

    Some areas where people previously parked informally on Hardinge Street will no longer be available for safety reasons, including safe sight distance requirements and the new road layout. New marked parking bays will be established in safe locations.

    Why is parking changing?

    The new road has been designed to improve safety by adding channelised turning lanes and increasing safe sight distances at intersections. Parking in some areas can block driver visibility, so parking will only be marked and signed in areas that are safe.

    Can I park outside my house?

    Only if there is a marked parking bay. If you have concerns about parking near your property, please contact the project team to discuss your situation.

    Where can trucks and caravans park when the project is finished?

    When the road is complete, marked parking bays will be available for trucks, cars and caravan/trailers in designated safe areas. Most parking in the industrial area between Ochtertyre and Wood Streets will be retained and marked for long vehicles.

    Will timed parking restrictions be introduced?

    Timed parking is not currently planned. If timed restrictions are considered in the future, affected businesses and residents will be consulted.

Rams Oval Access

    How do I access Rams Oval when the Hardinge Street entrance is unavailable?

    The alternative access on Ochtertyre Street has been upgraded to accommodate extra traffic.

    Where can I park for Rams Oval?

    Parking inside the oval remains as normal. Parking on Hardinge Street may not be available during construction, so please allow extra time to find alternative parking when attending the oval.

    What traffic management will be in place on game days?

    Traffic management will be provided if required. Please follow the directions of traffic controllers and drive carefully near workers, pedestrians and machinery.

Heavy Vehicles and Over Size Mass (OSOM) Vehicles

    How will the road design affect heavy vehicles?

    The road has been designed to improve safety by adding channelised turning lanes and increasing safe sight distances at intersections. Channelisation separates turning and through traffic, creating safer and more efficient traffic flow.

    How will channelisation affect trucks and OSOM vehicles?

    The road has been designed to accommodate heavy vehicle movements, including Over Size Over Mass vehicles, with features such as mountable medians, low profile kerbs, removable or layover signage and road widening at key intersections.

    Why has a concrete median strip been included?

    Hardinge Street has a mix of heavy vehicles, freight vehicles, buses, cars, motorcycles, bicycles and pedestrians. The concrete median and turning lanes are included to separate turning vehicles from through traffic, support safer traffic flow and improve safety for all road users.

    How have pedestrians and cyclists been considered in the design?

    The design allocates space for all road users and includes features such as pedestrian refuge islands, tactile treatments, new footpaths in some areas, line marking and signage to improve safety and visibility.

    Why is channelisation included between Wood Street and Harfleur Street?

    Channelisation is included to create a consistent road layout, reduce driver confusion, separate turning traffic from through traffic and reduce the risk of rear-end and intersection crashes.

    Will the roadworks affect heavy/OSOM vehicle movements?

    Oversize and overmass (OSOM) vehicles wider than 3.5 metres can only travel through the work zone during standard working hours from 7am to 5pm Monday-Friday, and up to 1pm on Saturdays.

    Drivers should stop at the designated pull-over areas and contact traffic control on UHF Channel 27 or the mobile phone 0437 969 287 before driving through the work area.

    Traffic control including a reduced speed limit of 40 km/h and partial lane closures will be in place. There are no detours in place for this project. 

    Operators or pilots are advised to pre-plan the route and contact the project team in advance to coordinate access through the site.

    Designated Pull-over areas:

    • Parking area adjacent to the Deniliquin Oval, corner Ochtertyre and Hardinge streets (for northbound traffic)
    • Davidson Street Rest Area (for southbound traffic

    For the latest traffic information, visit www.livetraffic.com/incident-details/269975 or download the Live Traffic NSW app.

Noise, Vibration and Environment

    Will there be much noise?

    There will be some noise and minor vibration from activities such as underground boring, water main works, kerb and gutter construction and road paving. The project team will take steps to reduce impacts as much as possible. If your residence has been identified as potentially affected by noise from night paving works, a Transport for NSW representative will consult with you. If you have questions on impacts of night paving works, please contact Ram Somisetty on 0437 969 287.

    Will there be dust or pollution?

    Some dust and construction impacts may occur. These will be managed through standard construction controls, including dust suppression and safe handling of materials.

    What will happen to trees and nature strips?

    No mature trees are planned to be removed. Existing trees will be retained and protected where needed. Some already disturbed vegetation in nature strips may be removed and replaced. New trees, shrubs and landscaping will be provided once construction activities allow. Consultation will occur with interested local groups regarding the selection of species to be planted.

    Will the project affect endangered species or protected habitat?

    The environmental impact is expected to be low. The works are mainly within an already disturbed road reserve and are not expected to significantly affect protected fauna habitat or threatened ecological communities.

    Are there any places of cultural, historical or social significance affected by the works?

    Searches undertaken for the project confirmed that no places or buildings with cultural, historical or social significance are expected to be affected by the works.

    Are there any long-term environmental effects expected?

    The project is not expected to have long-term negative environmental effects. Disturbed areas will be reinstated, and new landscaping and trees will improve the streetscape.

    What will happen to waste from the project?

    Where possible, project materials will be reused or recycled. Material that cannot be reused or recycled will be taken to an appropriate waste facility.

Notifications and Enquiries

    Where can I find the latest roadworks updates?

    Council’s Have Your Say engagement hub is the main source for project information:
     https://www.haveyoursay.edwardriver.nsw.gov.au/hardinge-street-road-reconstruction-project

    You can also view plans and fact sheets at Edward River Library or Council’s Customer Service Centre and Library, and follow Council’s Facebook page for updates.

    Who should I contact if I have a question that is not answered here?

    In the first instance, phone Council Customer Service on 03 5898 3000. If Customer Service cannot answer your question, they will direct your enquiry to the project team.

    How will affected residents and businesses be notified about changes?

    Council will provide updates through the Have Your Say project page, direct letters or emails where needed, signage, social media, fact sheets and other project communications.